Employer: TAMEX Obiekty Sportowe S.A.

Job: “Alteration, refurbishment and improvement of the MOSiR stadium in Mielec”

Period: 1/6/2011 to 20/2/2014

– Fabrication and erection of the steel structure of the complete roof including a platform for the press on the Eastern and Western Stand of the stadium and installation of corrugated sheets, multiwall polycarbonate and a drainage system

– Fabrication and erection of the complete galvanised steel structure of shops, including fireproofing to R 30 and wall and roof lining with EI 30 and EI 60 sandwich panels

– Fabrication and erection of complete players’ tunnels including the installation of multiwall polycarbonate

– Fabrication and erection of internal and external staircases, balustrades, railings, rails and ladders

 

This post is also available in: PLDEFRRU

PolandEnglishGermanFrenchRussia